In Proceeding No. 15AL-0048, the Company agreed to terms guiding the installation of customer sited storage facilities

This document provides guidance for the interconnection of electric storage to operate in parallel with the utility and a customer's renewable generation. The energy storage is connected on the renewable generation's side of the Production Meter in a net metering (NEM) arrangement. 

The full document can be read here.

Visit the Regulation & Public Policy Page on the Distributed Photovoltaics (DPV) Toolkit for more resources on this topic.